The ENTSO-E Regional
Group Continental Europe at its plenary meeting of
17th April 2013
has decided the increase of the transfer
capacity to/from
Turkey
as follows:
Current (old) Capacities
|
New Capacities
|
Turkey importing from CESA
|
400 MW
|
550 MW
|
Turkey exporting to CESA
|
300 MW
|
400 MW
|
Conditions for implementing above new values of transfer capacities are:
a) Increase the overload protection settings of the two tie lines from Bulgaria
b) Implementation of a new function in the Special Protection Scheme
(SPS) at Hamitabat S/S in Turkey
See also
https://www.entsoe.eu/news-events/announcements/newssingleview/article/cross-border-capacity-between-bulgaria-greece-and-turkey-to-increase/?tx_ttnews%25255BbackPid%25255D=43&cHash=73c963fdfeb7fe929a8fefb0c57e5657
Said capacities shall be allocated at
the borders
Bulgaria
–
Turkey
and
Greece
–
Turkey
at a rate of 2/3 and 1/3 respectively, as also done in the past.
Since the implementation of the new function in the SPS in
Turkey
is expected to be installed and tested by the first two weeks of June
2013, the monthly auctions for the month of June 2013 will be done with current
(old) capacities as of the table above.
As soon as the implementation and testing of the new function of the SPS in
Turkey
is completed, daily auctions will be done for the remaining days of
June, for additional available capacities by the Bulgarian and Greek TSOs, for
their respective capacity volume increase.
According to the current time schedule, the new increased capacities will be
available through monthly auctions for the month of July 2013. Market
participants will be informed accordingly by a new announcement at the sites of
the involved TSOs.