Following regular trial tests, Unit A-5 returned to operation at around 11:50 a.m. on May 6 and was synchronised with the grid, KEK said in a statement on Sunday.
In April, local media reported that KEK ex-head Nagip Krasniqi was arrested for acting in violation of public procurement rules by awarding Swiss company Litwin a 3.5 million euro ($3.86 million) contract for repairs of the unit’s turbine. Krasniqi was charged with abuse of authority, exercise of influence and conflict of interest.
The A-5 unit was shut down in July 2022 for regular maintenance.
Repairs at the Kosova B thermal power plant are proceeding according to schedule, KEK also said. The overhaul of unit B-2 started on April 16 and is expected to be completed after three months when the three-month overhaul of unit B-1 is planned to begin.
(SeeNews, May 8, 2023)