Vestas Wind Systems Gets 570MW Order In California

Vestas Wind Systems Gets 570MW Order In California
dj
Πεμ, 22 Ιουλίου 2010 - 16:53
Vestas Wind Systems said late Wednesday it has received a 570MW order for 190 V90-3.0 MW turbines for Terra-Gen's Alta Wind Energy Center near Tehachapi, California, U.S.A.

Vestas Wind Systems said late Wednesday it has received a 570MW order for 190 V90-3.0 MW turbines for Terra-Gen's Alta Wind Energy Center near Tehachapi , California , U.S.A.

	
	 MAIN FACTS: 
-The order has been placed by subsidiaries of Alta Wind Holdings, LLC, a wholly-owned subsidiary of Terra-Gen Power, LLC.

-Terra-Gen's V90-3.0 MW purchase is Vestas' largest order for a single site.

-The Alta project also sets several important benchmarks:

-It will be one of the largest wind power plants in the
U.S.A.

-Together the bank financing, bond issue and the sale leaseback financing of the Alta project is the largest financing of a North American wind-energy project and the first wind-energy leveraged lease to be placed in the debt capital markets.

-The contract includes delivery and commissioning as well as a five-year service and maintenance agreement.

-Delivery is scheduled for late 2010.

-The first 50 turbines will be commissioned by the end of 2010 and the remaining ones will be online in the first half of 2011.

-Vestas' manufacturing operations in
Colorado , U.S.A, will produce wind components for this order.

-All blades for the Alta project will be produced at Vestas' blades factory in
Windsor , Colorado . And a majority of the towers will be manufactured at Vestas' new tower factory in Pueblo , Colorado .

-The
Alta Wind Energy Center is supported by a 1,550 MW power purchase agreement with Southern California Edison to sell renewable energy.

-This order marks Vestas' eighth North American deal announced in 2010, totaling 1,336 MW this year among four turbine types.

-The above order does not affect Vestas' expectations for 2010.